Severn 8 at RBL1148, 8 Severn Road, The Peak, H.K.
  • Date of Commencement
    2003-03
  • Date of Completion
    2005-09
  • Main Contractor
    Yee Fai Construction Co. Ltd.
  • Consultant
    J. Roger Preston Ltd.
  • Architect
    LWK & Partners (HK) Ltd.
  • Client
    Sun Hung Kai Properties Ltd.
Caribbean Coast, Package 3, TCTL5, Tung Chung
  • Date of Commencement
    2002-03
  • Date of Completion
    2004-07
  • Main Contractor
    Hong Kong Construction (Holdings) Ltd.
  • Consultant
    Parsons Brinckerhoff (Asia) Ltd.
  • Architect
    Hsin Yieh Architects & Engineers Ltd.
  • Client
    Cheung Kong (Holdings) Ltd.
Liberté at NKIL 6328, Lai Chi Kok Road, Kowloon
  • Date of Commencement
    2001-02
  • Date of Completion
    2003-06
  • Main Contractor
    Yee Fai Construction Co. Ltd.
  • Consultant
    J. Roger Preston Ltd.
  • Architect
    LWK & Partners (HK) Ltd.
  • Client
    Sun Hung Kai Real Estate Agency Ltd. & Shun Tak Group
No. 35 Deep Water Bay Road, Hong Kong
  • Date of Commencement
    2001-12
  • Date of Completion
    2002-11
  • Main Contractor
    Gammon Construction Ltd.
  • Consultant
    Wong & Ouyang (Building Services) Ltd.
  • Architect
    Wong & Ouyang (HK) Ltd.
  • Client
    Kerry Properties Ltd.
Aegean Coast, TMTL 374, Area 55A, So Kwun Wat, Tuen Mun
  • Date of Commencement
    2000-12
  • Date of Completion
    2002-09
  • Main Contractor
    E Man - Sanfield JV Construction Co. Ltd.
  • Consultant
    J. Roger Preston Ltd.
  • Architect
    Wong Tung & Partners Ltd.
  • Client
    Sun Hung Kai Real Estate Agency Ltd.
Prima Villa, STTL 394, Yuen Chau Kok, Shatin
  • Date of Commencement
    2000-12
  • Date of Completion
    2001-09
  • Main Contractor
    Chun Fai Construction Co. Ltd.
  • Consultant
    Sun Hung Kai Engineering Co. Ltd.
  • Architect
    CYS Associates (HK) Ltd.
  • Client
    Sun Hung Kai Properties Ltd.